Gare Nanterre La Folie – RER E

Gare Nanterre La Folie – RER E
Client: SNCF Réseau
Project management: TWIST consortium (Arcadis / Explorations Architecture)
Funding: French government, Île-de-France region, SGP, City of Paris, Hauts-de-Seine and Yvelines departments, Île-de-France Mobilités, SNCF Réseau.
Architect: Explorations Architecture
Programming: creation of a station for the westward extension of the RER E line
Terminus: Chelles/Tournan <> Nanterre La Folie (east branch of the RER E line)
Commissioning: 2024
Location: Groues district, Boulevard de La Défense (Nanterre)
The third new station in the Eole project (extension of the RER E line to the west) will be located on the Groues railway line.
This intermodal station in the heart of the renovated Groues district will contribute to its dynamism and the development of intermodality and soft modes of transport (bicycles, pedestrians, etc.). It will help to relieve congestion on the RER A line and will also be a possible alternative in the event of an incident, with a 5-minute walk between the two RER lines.
Passenger flows will be smoother, simpler, and connected to public spaces, thanks in particular to an imposing main entrance measuring 8 meters high by 12 meters wide. Fully accessible, it will welcome more than 10,000 passengers per day, with 22 trains during rush hour, 16 trains coming from the east and 6 from the west when it is fully operational between east and west.
The project to extend the RER E westward requires the development of storage tracks and a maintenance site for trains and infrastructure. The site known as the “railway island” north of Eole station (consisting of former warehouses and workshops) will be developed for the installation of storage tracks and a service building.
Key points and benefits of the future station
- Nanterre-La-Folie station to open in spring 2024
- An intermodal station: bicycles, buses, metros, trains
- A 12-meter-wide pedestrian bridge serving the station's four 225-meter-long platforms
- Six tracks
- Frequent trains: 22 trains during rush hour
- Two road bridges improving accessibility and connections between the Terrasses and Groues neighborhoods
Future RER E journey times
- Nanterre - Porte Maillot in 6 minutes compared to 12 minutes today
- Nanterre – Magenta in 12 minutes compared to 25 minutes today
- Nanterre- Mantes-la-Jolie in 37 minutes compared to 57 minutes today
Planning
- 2015-2017: Preparatory work
- 2017-2020: Civil engineering work
- 2020-2022: Laying of tracks and catenary wires and installation of railway signaling
- 2022-2023: Development of platforms and footbridge and finishing work on station premises
- 2023-2024: Finishing touches and testing