Construction site infos

The Park: work on the grounds surrounding the Neuilly Défense residence and the CB21 tower

From mid-February to July 2026

Paris La Défense is continuing with the second phase of the park development project launched in January. Starting on 16 February 2026 and lasting five months, work to replace slabs and waterproofing will be carried out around the Neuilly Défense residence and the CB21 tower. The staircase and ramp connecting the two will be replaced by a wide ramp with a slope that will facilitate accessibility, particularly for people with reduced mobility.  

Légende du plan - phase est

Zone bleu-vert : Zone chantier – Phase Est rampe escalier CB21 – mi-février 2026 à juillet 2026
Zone jaune : Zone chantier Phase Est Rampe Neuilly Défense –mi-février 2026 à juillet 2026
Zone rouge : Zone chantier Phase Est actuelle

Les accès aux immeubles, au métro ligne 1 et les issues de secours seront maintenus durant toute la durée du chantier.

Horaires de chantier : du lundi au vendredi de 7h30 à 12h00 et de 13h00 à 16h30. Pas de travaux bruyants avant 8h et entre 12h00 et 14h00. Pas de travaux le week-end, ni les jours fériés.

Pour toute demande, merci de nous envoyer un mail sur l’adresse vu@parisladefense.com

The Neuilly Défense ramp construction phase – from mid-February to July 2026

  • Setting up the work site,
  • Removing slabs and blocks,
  • Cleaning and installing new waterproofing,
  • Installing the drainage layer and lightweight backfill,
  • Laying cables and installing lighting fixtures,
  • Laying new slabs,
  • Replacing granite kerbs.

Stage of work on the CB21 stair ramp - mid-February to July 2026

  • Establishment of the construction site,
  • Removal of slabs and blocks and demolition of existing stairs and ramp,
  • Cleaning and installation of new waterproofing,
  • Construction of the new ramp,
  • Installation of the drainage layer and lightweight backfill,
  • Installation of utilities and lighting fixtures,
  • Laying of new slabs.